The future of the Postsportareal in Vienna-Hernals remains controversial. The Federal Administrative Court (BVwG) has annulled an Austrian Post AG tender for the future operation of sports facilities. The decision affects around 70 percent of the 15-hectare site.
The court said that the requirements for the planned term of the operating concession had not been sufficiently justified. Nevertheless, Austrian Post intends to stick to its plans to award a new contract from the beginning of 2028.
The decision centres on the proposed total contract term of 40 years. This included a minimum term of 25 years and an option to extend it by a further 15 years.
The Federal Administrative Court objected that Austrian Post had not provided sufficient economic justification for this lengthy term.
Under the Federal Concessions Procurement Act, terms exceeding five years require supporting calculations. These are intended to show how long an operator needs to recoup its investments.
According to the court, no financial viability calculation meeting the statutory requirements could be provided.
Since the contract term is a key part of the tender, the defect could not be remedied by a simple amendment. The court therefore declared the entire tender in question null and void.
Numerous sports clubs are active at the Postsportareal. Nearly 30 clubs currently use the site.
The current operator is Post SV. According to ORF, around 5,000 athletes are affiliated with the club.
The site offers a range of sports, including football, tennis, field hockey, volleyball and mini golf.
Post SV had challenged the Post’s tender processes. In the club’s view, the requirements were too vague for it to apply to operate the site in future under fair conditions.
The Federal Administrative Court’s decision concerns the tender for non-profit club and school sports. However, it does not automatically mean that Post SV will continue to operate the site after 2027.
Post Intends to Proceed with New Tender from 2028Despite the legal setback, Österreichische Post AG is sticking to its schedule.
Post spokesperson Markus Leitgeb told ORF that the company is still aiming for a contract term of 40 years. The necessary financial calculations will now be prepared by an external party.
Post still intends to award a new contract for the site from the beginning of 2028.
The current lease with Post SV expires at the end of 2027.
It is currently unclear whether the planned new tender can actually be carried out within the intended timeframe following the court’s decision.
Further Decisions Expected in DecemberThe tender that has now been annulled is only one part of the overall procurement process.
Post had conducted a total of three tenders for different uses of the site.
The Federal Administrative Court is scheduled to hear the two other tenders on December 2 and 11, 2026.
According to ORF, the “Save Post SV” initiative hopes that these proceedings will also be annulled. It is campaigning to preserve the site as a unified location for non-profit sports in the long term.
What Is Planned for the Postsportareal?Regardless of the current procurement dispute, the City of Vienna and Post are working on further developing the site.
As VIENNA.AT reported in October, sports are to remain the centerpiece of the 15-hectare site.
Among other things, the current plans include around 6,000 square meters of additional green and open spaces, new public paths, and a multipurpose hall.
Housing is also planned. According to previous announcements, new buildings are to be constructed primarily on land that has already been sealed or built on. Two-thirds of the newly zoned apartments are to be built as subsidized housing.
Facilities for everyday needs are also being discussed, such as a kindergarten, restaurants or a supermarket.
The Federal Administrative Court’s decision does not automatically overturn these development plans. It specifically concerns the tendering process for non-profit club and school sports.
What Happens Next?The next important dates are the court hearings on December 2 and 11, 2026, concerning the two remaining tenders.
For the sports clubs, the key questions are who will operate the site after the current lease expires at the end of 2027, and under what conditions the sports facilities can be used in the future.
Swiss Post remains committed to awarding a new contract from the beginning of 2028. However, no final solution for future operations has yet been determined.
(Ed.)
Auf dem Areal werden unter anderem Fußball, Tennis, Landhockey, Volleyball und Minigolf angeboten.
Der Post SV hatte die Ausschreibungen der Post angefochten. Aus Sicht des Vereins waren die Vorgaben zu unkonkret, um sich unter fairen Bedingungen um den künftigen Betrieb bewerben zu können.
Die Entscheidung des Bundesverwaltungsgerichts betrifft nun die Ausschreibung für den gemeinnützigen Vereins- und Schulsport. Sie bedeutet allerdings nicht automatisch, dass der Post SV das Gelände auch nach 2027 weiter betreiben wird.
Trotz des gerichtlichen Rückschlags hält die Österreichische Post AG an ihrem Zeitplan fest.
Post-Sprecher Markus Leitgeb erklärte gegenüber dem ORF, dass weiterhin eine Vertragslaufzeit von 40 Jahren angestrebt werde. Die dafür notwendigen wirtschaftlichen Berechnungen sollen nun extern erstellt werden.
Die Post möchte das Gelände weiterhin ab Anfang 2028 neu vergeben.
Der aktuelle Pachtvertrag mit dem Post SV läuft Ende 2027 aus.
Ob die geplante Neuvergabe nach der Gerichtsentscheidung tatsächlich im vorgesehenen Zeitraum umgesetzt werden kann, ist derzeit offen.
Die nun aufgehobene Ausschreibung ist nur ein Teil des gesamten Vergabeverfahrens.
Die Post hatte insgesamt drei Ausschreibungen für unterschiedliche Nutzungsbereiche des Areals durchgeführt.
Über die beiden weiteren Ausschreibungen soll am Bundesverwaltungsgericht am 2. und 11. Dezember 2026 verhandelt werden.
Die Initiative „Rettet den Post SV“ hofft laut ORF darauf, dass auch diese Verfahren aufgehoben werden. Sie setzt sich dafür ein, dass das Gelände langfristig als zusammenhängender Standort für den gemeinnützigen Sport erhalten bleibt.
Unabhängig vom aktuellen Vergabestreit arbeiten die Stadt Wien und die Post an einer Weiterentwicklung des Geländes.
Wie VIENNA.AT bereits im Oktober berichtete, soll der Sport weiterhin das Herzstück des 15 Hektar großen Areals bilden.
Die bisherigen Pläne sehen unter anderem rund 6000 Quadratmeter zusätzliche Grün- und Freiflächen, neue öffentliche Wege sowie eine Mehrzweckhalle vor.
Auch Wohnbau ist geplant. Neue Gebäude sollen laut den bisherigen Ankündigungen vor allem auf bereits versiegelten oder bebauten Flächen entstehen. Zwei Drittel der neu gewidmeten Wohnungen sollen gefördert errichtet werden.
Ergänzend sind Einrichtungen für den täglichen Bedarf im Gespräch, etwa ein Kindergarten, Gastronomie oder ein Supermarkt.
Die Entscheidung des Bundesverwaltungsgerichts hebt diese Entwicklungspläne nicht automatisch auf. Sie betrifft konkret das Vergabeverfahren für den gemeinnützigen Vereins- und Schulsport.
Die nächsten wichtigen Termine sind die Gerichtsverhandlungen am 2. und 11. Dezember 2026 zu den beiden übrigen Ausschreibungen.
Für die Sportvereine bleibt vor allem entscheidend, wer das Areal nach dem Auslaufen des bestehenden Pachtvertrags Ende 2027 betreiben wird und unter welchen Bedingungen die Sportanlagen künftig genutzt werden können.
Die Post hält an einer Neuvergabe ab Anfang 2028 fest. Eine endgültige Lösung für den künftigen Betrieb steht jedoch noch nicht fest.
(Red)