The South Motorway (A2) is now open to traffic on both lanes again after the landslide last December near Pinkafeld (Oberwart district).
Earlier than planned, the section can be released after work on the slope stabilization, explained Asfinag project manager Gerald Mühl on Wednesday. The dry weather in recent weeks has favored the stabilization of the embankment on which the A2 was built in this area.
The delays caused by the onset of winter at the end of February could thus be made up, said Mühl. Just in time for the Easter travel traffic, two lanes are now available in each direction. In parallel, the repair work will continue until mid-June. The slope, which slipped about five meters over a length of 40 meters, is being stabilized with further safety measures.